Road construction works on CB2 in Sankuawasabha
was completed in February 2011, whereas road construction works
on KJ2 in Achham was completed in April 2011. Before opening these
roads to traffic, the completed roads were jointly monitored by
DDC officials and district party representatives to assure that
the roads fully complied to design standards and the in-service
performance criteria specified for RAP2 roads. Construction work
of the remaining nine road corridors continued as planned until
start of this year monsoon.
The detailed progress status of road construction
of each road corridor is presented in Annex C: Monitoring Sheets
with the summary of physical progress of all road corridors in Figure
2.2. The overall progress achieved varies between different RAPII
road corridors. Construction progress in the Progress at a glance,
shows that DP2 in Doti and BG2 & HD2 in Bhojpur are lagging behind
compared to the progress recorded on other RAPII road corridors.
Most of the remaining works include rock breaking and construction
of gabion retaining walls in kholas/kholsas and other sections where
sufficient road width are not readily available due to reluctance
of local communities to part with their land.
Progress details related to physical and financial
aspects are presented in the following charts, figures and tables.
| |
Table: Road corridors
physical progress by June 2011 |
|
|
| District |
Road
corridors |
Physical
Progress ('000 cu. m.)
|
| Earthworks |
Structures |
Estimated
quantity |
Completed
% |
Estimated
quantity |
Completed
% |
| Doti |
Dipayal–Patihalne
(DP2 : 22.3km)
|
197 |
61% |
41 |
68% |
|
Doti |
Rajpur–ChamaraChautara
(RC2 : 31.0km) |
233 |
81% |
45 |
66% |
|
Achham |
KamalBazaar–
Jungalghat (KJ2 : 15.3km) |
98 |
100% |
40 |
100% |
|
Achham |
Timilsen– Ramaroshan
(TR2 : 23.0km)
|
201 |
67% |
58 |
70% |
|
Dailekh |
Ramghat– Singhasen
(RS2 : 14.8km)
|
149 |
92% |
35 |
76% |
|
Dailekh |
Desigade–Mahabu
(DM2 : 12.0km)
|
142 |
77% |
29 |
70% |
|
Dailekh |
Chupra – Meheltoli
(CM2 : 20.5km)
|
190 |
87% |
39 |
85% |
|
Khotang |
Diktel–Khotang Bazaar
(DK2) - 50km
|
593 |
87% |
106 |
84% |
|
Bhojpur |
Bhojpur–Ghodetar
(BG2 : 35.0km)
|
403 |
80% |
87 |
64% |
|
Bhojpur |
Hile Bhanjyang – Dingla
(HD2 : 35km)
|
314 |
72% |
68 |
69% |
|
San'wasabha |
Chainpur–Barhabise
(CB2 : 36.2km)
|
115 |
100% |
30 |
100% |
|
Terhathum |
Myanglung–Sankranti
Bazaar (MS2 : 67.0km) |
297 |
85% |
46 |
82% |
|